MEPCO New Connection 2026 – Apply for Electricity Connection Online
Need a new electricity connection for your home, shop, or factory in Multan, Dera Ghazi Khan, Bahawalpur, Sahiwal, Khanewal, Vehari, Lodhran or other MEPCO service areas? This guide walks you through the entire process – online application, required documents, fees, and expected timeline – so you can get your MEPCO connection without hassle.
Step-by-Step Application Process for MEPCO New Connection
- Choose application method: Online via MEPCO customer portal or offline by visiting the nearest MEPCO Customer Service Center (CSC).
- Fill application form – Download from MEPCO website or collect from CSC. Provide property details, load required (kW), and consumer type (domestic/commercial).
- Submit required documents (see list below). For online application, upload scanned copies.
- Pay the fee – Demand notice will be issued after document verification. Pay via bank challan or online (credit/debit card, JazzCash).
- Site inspection – MEPCO technical staff inspects the property within 7-10 days.
- Meter installation – After approval, meter is installed and connection is energized within 15-30 days from application date.
Processing time: Typically 2-4 weeks for domestic connections. Express processing available for urgent cases (additional fee).
Required Documents for MEPCO New Connection
- Copy of CNIC (applicant / property owner)
- Proof of ownership (registry / allotment letter / possession letter)
- Site plan / layout of premises
- Passport-size photograph (2 copies)
- For rented property: rent agreement + landlord’s NOC
- For commercial connection: business registration certificate / NTN (if applicable)
All documents must be attested. Bring originals for verification during site inspection.
MEPCO New Connection Fee Structure (Approximate)
- Domestic 1-phase (up to 5 kW): Application fee + meter security + wiring inspection → ~Rs 10,000 – 15,000
- Domestic 3-phase (5-15 kW): ~Rs 25,000 – 35,000
- Commercial 1-phase: ~Rs 15,000 – 20,000
- Commercial 3-phase: ~Rs 35,000 – 50,000
Final amount depends on load (kW) and voltage. A demand notice will be issued after application verification. You can pay through bank challan (Habib Bank, National Bank, etc.) or online via MEPCO portal.
Apply Online – MEPCO Customer Portal
- Visit MEPCO’s official customer portal: https://mepco.com.pk/new-connection.
- Register with your CNIC and mobile number.
- Fill the application form with property details and load requirement.
- Upload scanned copies of required documents (CNIC, ownership proof, site plan).
- Submit and note down the application reference number.
- Check status online. MEPCO will contact you for site inspection and fee payment.
Alternative offline method: Visit your nearest MEPCO Customer Service Center (list of centers available on MEPCO website).
Frequently Asked Questions
How long does MEPCO take to give a new connection?
Typically 15-30 days after complete application and fee payment. For rural areas, it may take up to 45 days due to infrastructure extension.
Can I apply for a new MEPCO connection online from anywhere?
Yes. The online portal accepts applications from anywhere. However, the property must be within MEPCO service area (Multan, DG Khan, Bahawalpur, Sahiwal, Khanewal, Vehari, Lodhran).
What is the minimum load for a domestic connection?
Minimum is 1 kW (approx 4-5 fans + lights + refrigerator). For a standard 1-bedroom apartment, 2-3 kW is sufficient.
Estimate Your Future MEPCO Bill
Once you get your new connection, use our MEPCO Bill Calculator to estimate monthly charges based on expected consumption. It uses official NEPRA tariff slabs to help you budget.